Awaab’s Law Phase 2: what changes on 30 November 2026

Moisture meter reading on a mouldy bedroom wall

On 30 November 2026, Awaab’s Law stops being about damp and mould.

Since 27 October 2025, social landlords in England have worked to fixed timescales for damp and mould: investigate a significant hazard within 10 working days, make it safe within 5 working days of that investigation, and deal with emergency hazards within 24 hours.

Phase 2, confirmed by Housing Minister Matthew Pennycook on 13 July 2026, applies those same clocks to seven more hazard categories:

  • excess cold
  • excess heat
  • falls and trip risks
  • structural collapse and falling elements
  • fire and explosion risks
  • electrical hazards
  • domestic hygiene, including pest infestations

The timescales do not change. The number of things they apply to does.

Why this is a bigger change than it looks

Damp and mould, for all the harm it causes, is usually visible and usually reported. A tenant sees a stain spreading across a bedroom wall and tells somebody. The duty is triggered by a complaint, and most landlords have built their Phase 1 response around handling that complaint faster.

Phase 2 is different, and the difference matters.

Excess cold, structural collapse, falling elements, falls, electrical risk — these are largely built-in. They come from how a building was designed, built or altered, not from how it is being lived in. A solid-wall property with no insulation and a failing heating system is cold by construction. A parapet or a canopy does not become unsafe on the day somebody notices it. Nobody phones to report the lintel they cannot see.

So the operational question changes. Phase 1 asked: can you respond quickly enough once a tenant tells you? Phase 2 asks something harder — do you already know what is in your stock?

Because the clock starts when the landlord becomes aware of a hazard, and “aware” includes what you find yourself, not only what a resident reports. A survey programme that turns up an unsafe structural element starts the same clock a phone call would.

That cuts both ways, and it is worth being honest about it. Finding things creates duties. But the alternative is finding them the way Awaab Ishak’s family found theirs.

Excess cold is the one most landlords are underestimating

Of the seven, excess cold is the category most likely to appear at scale across a portfolio, and the least likely to arrive as a complaint. Tenants rarely report being cold as a housing hazard. They report a high bill, or they say nothing and go without heating.

It is also the category where the remedy is slowest. You cannot resolve a fundamentally cold home inside five working days with a repair. Insulation, heating and ventilation work is a programme, not a job ticket — which means the properties most exposed need to be identified well before anybody is standing in one with a clock running.

If you already hold EPC or retrofit assessment data, you are part of the way there. If that data is more than a few years old, or was modelled rather than surveyed, it is worth checking what it actually tells you about the homes at the bottom of your stock.

What is worth doing in the next seven weeks

Seven weeks is not long enough to survey a portfolio. It is long enough to know where you stand.

  1. Work out what you actually hold. For each of the seven categories, can you say which properties are affected without visiting them? For most landlords the honest answer is yes for excess cold, patchy for structural and falls, and no for the rest.
  2. Find the gaps that are concentrated. Non-traditional construction, pre-1919 stock, anything with a known common defect across a block or an archetype. Hazards that repeat are the ones that generate repeat duties.
  3. Decide how a survey finding reaches the repairs system. If a surveyor spots a Phase 2 hazard on site and it sits in a report for three weeks, the clock has been running the whole time. The handover route matters as much as the survey.
  4. Treat excess cold as a programme, not a hazard queue. It belongs with your retrofit and energy planning, not with responsive repairs.
  5. Get the evidence trail right. What was found, when, what was done, by whom. Phase 2 does not only require action — it requires you to be able to show it.

How we can help

We carry out stock condition surveys for housing associations, local authorities and principal contractors across the UK — element by element, to one consistent standard, returned in a form your asset management system can use rather than as a pile of PDFs.

We also carry out independent damp and mould inspections, which identify the cause rather than recording the symptom, and energy efficiency work covering EPC, retrofit assessment and the whole-house approach that excess cold ultimately needs.

If you want to know where your stock stands before 30 November, tell us the size and type of the portfolio and what the data is for, and we will tell you how we would approach it.

Talk to us


This article is general information about the Social Housing (Regulation) Act 2023 and the Awaab’s Law timescales. It is not legal advice. Landlords should confirm their obligations with their own advisers.